Foundation
Signs of foundation problems in Los Angeles homes
The cracks, sloping floors and sticking doors worth an inspection, and the ones that are only cosmetic.
Brace and bolt strengthens older houses on raised foundations. Soft-story retrofits are a separate program for larger buildings.
Short answer
A brace and bolt retrofit bolts an older wood-frame house to its foundation and braces the short cripple walls under the floor. A soft-story retrofit is different: Los Angeles requires it for older wood-frame buildings with open ground floors, such as tuck-under parking, and it does not apply to buildings with three or fewer units.

It anchors the house to its foundation and braces the short walls under the floor. The Earthquake Brace + Bolt program says a retrofit is either brace and bolt, where short cripple walls of 4 feet or less are braced with plywood or OSB sheathing and the foundation is bolted to the frame, or bolt only, where the frame sits directly on a stem wall. It also requires the water heater to be strapped and braced.
The California Earthquake Authority defines cripple walls as short frame walls that extend from the foundation to the bottom of the first floor.
Older wood-frame houses on raised foundations. The program says its retrofit is only done on wood-framed, pre-1980 homes with a raised foundation, and that the work must follow California Existing Building Code Chapter A3. Registration for its grants opens only for a limited time each year, so check the program's site for the current status.
Related guide: Signs of foundation problems in Los Angeles homes
It is a building with a weaker first floor that cannot carry the weight of the stories above it in an earthquake. The LADBS owner guide says the first floor generally has large openings in the perimeter walls, such as garages, tuck-under parking or large windows. LADBS says many wood-frame soft-story buildings caused loss of life, injury and property damage in the Northridge Earthquake.
A building is covered when it has two or more stories of wood frame, was built under codes enacted before January 1, 1978, and has ground floor parking or similar open space. The program does not apply to residential buildings with three or fewer units.
The owner must hire a California-licensed engineer or architect to evaluate the building and prepare retrofit plans, and must notify tenants in writing. LADBS says the owner then submits proof of a previous retrofit, plans to retrofit, or plans to demolish. The guide sets deadlines of 2 years, 3.5 years and 7 years from the date of the Order for those steps, the permit, and completed construction.
The program says its base grant is up to $3,000 toward a code-compliant retrofit, for wood-framed homes built before 1980 with a raised foundation. A supplemental grant may cover up to 100 percent of the retrofit cost, based on available funds, for households with income of $94,480 or less. The program page says those supplemental grants are selected first come, first served, and that income is verified with the IRS.
Registration opens only for a limited time each year, and homeowners are then randomly selected and notified by email. The program does not cover chimney work. The page states that the grants are funded by the California Earthquake Authority's Loss Mitigation Fund and FEMA's Hazard Mitigation Grant Program. The amounts above are as the program pages show them today, so check the program site for current figures and whether registration is open.
It can. The California Earthquake Authority offers discounts on its single-family home policies for a retrofit, and homeowners may get up to 25 percent off if the house meets its criteria. For a raised foundation, the discount is 25 percent for homes built in 1939 or earlier and 20 percent for homes built from 1940 to 1979. For other non-slab foundations it is 15 percent and 10 percent. Slab foundations get no discount, because the CEA says their premium already reflects lower earthquake risk.
To qualify, the home must be a one-to-four unit wood-frame dwelling built before 1980, with its water heater secured to the frame. A professional must verify the retrofit, and the owner sends a CEA Dwelling Retrofit Verification form or a valid Brace + Bolt verification number to the insurer. Ask your own insurer what applies to your policy.
Yes, a permit is expected. The Earthquake Brace + Bolt program says you or your contractor must get a permit from your local building department after you are accepted and before the retrofit begins. FEMA's retrofit plan set for crawlspace houses says building permits are always required for the work it describes. It also says inspections may be required for anchor bolts, wood panels on cripple walls, metal connectors, tie-downs and the final inspection.
LADBS lists adding sill plate anchor bolts and cripple wall plywood under Los Angeles Standard Plan No. 1 as work eligible for an Express Permit, for houses and residential buildings up to 3 stories and 4 units. Fees, plans and inspections vary by project, so confirm the current steps for your address with LADBS.
LADBS says California requires every water heater to be strapped against movement in an earthquake, and a restraint kit approved by the Office of State Architect is one way to do it. LADBS says to strap the heater in at least two places, the upper one-third and the lower one-third. The lower strap must sit at least 4 inches above the control unit.
The bulletin calls for lag screws at least 1/4 inch in diameter, with at least 1-1/2 inches of thread going into a wall stud, and a large flat washer under each. It says perforated plumber's tape is not acceptable for heaters over 40 gallons. The clearances printed on the heater's nameplate matter too. The brace and bolt program also requires the water heater to be properly strapped and braced.
FEMA publishes a ready-made plan set, FEMA P-1100 Volume 2A, for retrofitting crawlspace houses, and it covers anchoring the house to its foundation and bracing cripple walls. The plan set says it is for use by a general contractor or homeowner without necessarily involving a registered design professional. It applies only when the house has unoccupied space under the lowest framed floor, cripple walls no taller than 7 feet, and a downhill slope of no more than 20 percent.
FEMA is plain about the limits. The plan set says it is meant to improve earthquake performance, not prevent damage, and that it does not address every weakness in a home. It also says it deals with a single vulnerability. If a home does not match the eligibility questions, the plan set says a registered design professional must be involved.
Call one if you own an older house with a raised foundation or crawl space and want to know whether brace and bolt work applies. MLE Construction is a licensed general contractor (CSLB #1066995) in Tarzana that prepares plans and handles permits when the work needs them, and gives a detailed scope of work after an on-site visit. For a soft-story building, the LADBS guide starts with a licensed engineer or architect.
Next step: see our earthquake retrofit page, browse all foundation and structural services, or contact us for a free estimate.
It ties the house to its foundation and braces weak lower walls so the structure moves with the ground more safely. This reduces the risk of damage in an earthquake. It does not make a house earthquake-proof.
It may be if living space sits above a ground floor with large openings, such as garage or parking bays, and was built in an older style. An inspection and an engineer's review can confirm it.
Common signs include cracks in walls or stucco, doors and windows that stick, and floors that slope. Gaps between walls and ceilings are another clue. Many cracks are only cosmetic, and an inspection tells you whether yours are.
Yes. Call (800) 209-2779 or send the form and we will schedule a visit and give you a detailed scope of work.

Foundation
The cracks, sloping floors and sticking doors worth an inspection, and the ones that are only cosmetic.

Remodeling
Converting a garage to a unit means plans, city clearances and inspections. Here is how the Los Angeles process works.

Restoration
What a standard policy usually pays for, what it leaves out, and what to document before the cleanup starts.
Call or send the form. We will schedule a visit and give you a detailed scope of work.
Call Now(800) 209-2779Thank you.